City of Pinellas Park header
File #: 19-125    Name:
Type: Resolution Status: Consent Agenda
File created: 5/13/2019 In control: City Council
On agenda: 5/23/2019 Final action:
Title: AUTHORIZATION FOR CHANGE ORDER NO. 1 AND FINAL PAYMENT- City Parks Walking Trails Renovation Program - MTM Contractors, Inc.
Sponsors: Public Works
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

AUTHORIZATION FOR CHANGE ORDER NO. 1 AND FINAL PAYMENT- City Parks Walking Trails Renovation Program - MTM Contractors, Inc.

 

 

Body

NOTE:  Change Order No. 1 is recommended for approval so that the final payment of $83,776.10 can be processed and the contract closed out. Change Order No. 1 represents additional walking trail renovations at England Brothers Park, totaling $49,584.00, an increase of the original contract amount by 16.10%.  The change order will be charged to account 301781-562520, 19781/321-PROGRAM-CONSTRUT.  The final contract amount is $357,584.00.

 

 

Recommendation

ACTION:  (Approve - Deny) Authorization for approval and acceptance of Change Order No. 1, City Parks Walking Trails Renovation Program, an increase in the contract amount of $49,584.00, for a total adjusted contract amount of $357,584.00, and authorization for final payment of $83,776.10 to MTM Contractors., Inc. to be charged to the appropriate account.